# Task D.6.2 - Opportunity to Quotation Prefill & Project Timeline Fields
|
||||
|
||||
## Objective
|
||||
Improve the Opportunity -> Quotation workflow so users do not need to select the same Opportunity twice, while adding timeline fields and hot-project forecasting support.
|
||||
|
||||
## Requirements
|
||||
|
||||
### 1. Create Quotation from Opportunity Detail
|
||||
- Clicking `Create Quotation` from Opportunity detail must open the quotation form with the current Opportunity already selected.
|
||||
- Related customer/project/contact/product context should be prefilled where available.
|
||||
|
||||
### 2. Add Project Timeline Fields
|
||||
Add these fields to both Opportunity and Quotation:
|
||||
- `Project Close Date`
|
||||
- `Delivery Date`
|
||||
|
||||
Rules:
|
||||
- Use calendar date pickers.
|
||||
- Display format must be `YYYY-MM-DD`.
|
||||
|
||||
### 3. Auto Hot Project Rule
|
||||
- When `Project Close Date <= current date + 3 months`, the system should auto-suggest `hotProject = true`.
|
||||
- User may manually uncheck it.
|
||||
|
||||
### 4. Manual Override Rule
|
||||
Hot Project must support:
|
||||
- `auto suggested`
|
||||
- `manual override`
|
||||
|
||||
Recommended persisted fields:
|
||||
- `isHotProject`
|
||||
- `hotProjectAutoSuggested`
|
||||
- `hotProjectManuallyOverridden`
|
||||
|
||||
The UI must not keep forcing the checkbox back on during the same edit session after the user manually changes it.
|
||||
|
||||
### 5. Backend Enforcement
|
||||
Backend must:
|
||||
- accept `projectCloseDate`
|
||||
- accept `deliveryDate`
|
||||
- validate `YYYY-MM-DD`
|
||||
- calculate hot-project suggestion
|
||||
- preserve manual override
|
||||
- persist all values correctly
|
||||
|
||||
### 6. Quotation Prefill Rules
|
||||
When creating a quotation from an Opportunity, prefill where available:
|
||||
- `opportunityId`
|
||||
- customer / billing customer / project parties
|
||||
- project name
|
||||
- product type
|
||||
- branch
|
||||
- contact
|
||||
- `projectCloseDate`
|
||||
- `deliveryDate`
|
||||
- `hotProject`
|
||||
|
||||
Do not overwrite user edits after the form has already been opened.
|
||||
|
||||
### 7. UI Requirements
|
||||
Opportunity Detail:
|
||||
- `Create Quotation` must pass the current Opportunity context.
|
||||
- Quotation form shows selected Opportunity already filled.
|
||||
|
||||
Opportunity Form:
|
||||
- `Project Close Date`
|
||||
- `Delivery Date`
|
||||
- `Hot Project`
|
||||
|
||||
Quotation Form:
|
||||
- `Project Close Date`
|
||||
- `Delivery Date`
|
||||
- `Hot Project`
|
||||
|
||||
### 8. Testing
|
||||
Run:
|
||||
|
||||
```bash
|
||||
npm run typecheck
|
||||
npm run build
|
||||
npm run audit:pdf
|
||||
```
|
||||
|
||||
Test cases:
|
||||
- Create quotation from Opportunity detail preselects Opportunity.
|
||||
- User does not need to reselect Opportunity.
|
||||
- Project Close Date within 3 months auto-checks Hot Project.
|
||||
- User can uncheck Hot Project.
|
||||
- Project Close Date beyond 3 months does not auto-check.
|
||||
- Delivery Date saves correctly.
|
||||
- Quotation receives timeline fields from Opportunity.
|
||||
- Existing quotation create flow still works without Opportunity.
|
||||
|
||||
## Acceptance Criteria
|
||||
- Create Quotation from Opportunity detail preselects current Opportunity.
|
||||
- Opportunity does not need to be selected twice.
|
||||
- Opportunity has Project Close Date and Delivery Date.
|
||||
- Quotation has Project Close Date and Delivery Date.
|
||||
- Date fields use calendar pickers.
|
||||
- Hot Project is auto-checked when Project Close Date is within 3 months.
|
||||
- User can manually uncheck Hot Project.
|
||||
- Manual override is preserved.
|
||||
- Existing create/edit flows remain compatible.
|
||||
- Typecheck, build, and PDF audit pass.
|
||||
|
||||
---
|
||||
|
||||
## Implementation Result - 2026-07-01
|
||||
|
||||
Status: Completed
|
||||
|
||||
Summary:
|
||||
- Added `Project Close Date` and `Delivery Date` to opportunity and quotation persistence, DTOs, validation, and form UI.
|
||||
- Added shared hot-project auto-suggestion logic plus persisted `hotProjectAutoSuggested` and `hotProjectManuallyOverridden`.
|
||||
- Updated opportunity detail `Create Quotation` flow to pass current opportunity context into the quotation sheet, including project parties when already available.
|
||||
- Updated quotation prefill logic so automatic population no longer overwrites fields the user already edited in the same open session.
|
||||
|
||||
Verification:
|
||||
- `npm run typecheck` passed.
|
||||
- `npm run build` passed with existing Turbopack workspace-root and broad local storage path warnings.
|
||||
- `npm run audit:pdf` passed and refreshed PDF audit artifacts.
|
||||
|
||||
Implementation note:
|
||||
- [task-d.6.2-opportunity-quotation-prefill-project-timeline-2026-07-01.md](/C:/Users/mtpphtaps/Documents/gitea/alla-allaos-fullstack/docs/implementation/task-d.6.2-opportunity-quotation-prefill-project-timeline-2026-07-01.md)
|
||||