# Task AR.1 – Architecture Transition Plan
|
||
|
||
Status: Completed
|
||
|
||
Priority: Critical
|
||
|
||
Type: Solution Architecture / Transition Planning
|
||
|
||
Depends On
|
||
|
||
- BU-R.0 Business Blueprint Freeze
|
||
- BU-R.0.1 Workspace & Activity Blueprint
|
||
- BU-R.1 Business Capability Audit
|
||
|
||
---
|
||
|
||
# Objective
|
||
|
||
Produce the complete transition architecture from the current ALLA OS implementation to the approved Relationship-Driven Sales Operating Platform architecture.
|
||
|
||
This phase defines **how** the future architecture will be introduced while preserving the existing production foundation.
|
||
|
||
The primary goal is:
|
||
|
||
> Preserve the current production CRM foundation and extend it through new architectural layers rather than replacing existing domains.
|
||
|
||
This phase is architecture-only.
|
||
|
||
No production implementation is allowed.
|
||
|
||
---
|
||
|
||
# Background
|
||
|
||
Business Discovery has completed.
|
||
|
||
Business Blueprint has been frozen.
|
||
|
||
Business Capability Audit confirms that:
|
||
|
||
- Customer
|
||
- Contact
|
||
- Lead
|
||
- Opportunity
|
||
- Quotation
|
||
- Approval
|
||
- Organization
|
||
- RBAC
|
||
- PDF
|
||
- Dashboard
|
||
|
||
already provide a mature production foundation.
|
||
|
||
The remaining gaps are primarily cross-cutting capabilities:
|
||
|
||
- Activity Platform
|
||
- Timeline
|
||
- Calendar Workspace
|
||
- My Day
|
||
- Manager Workspace
|
||
- Executive Workspace
|
||
- Business Event Architecture
|
||
|
||
AR.1 defines how these capabilities are introduced without breaking the existing architecture.
|
||
|
||
---
|
||
|
||
# Architecture Principles
|
||
|
||
Every proposal must follow:
|
||
|
||
## Preserve Before Replace
|
||
|
||
Reuse existing production domains whenever possible.
|
||
|
||
---
|
||
|
||
## Extension Before Refactor
|
||
|
||
Prefer adding new architectural layers.
|
||
|
||
Avoid modifying existing domains unless unavoidable.
|
||
|
||
---
|
||
|
||
## Single Source of Truth
|
||
|
||
Every business concept must have one owner.
|
||
|
||
No duplicated lifecycle.
|
||
|
||
No duplicated status.
|
||
|
||
No duplicated business meaning.
|
||
|
||
---
|
||
|
||
## Projection over Duplication
|
||
|
||
Timeline
|
||
|
||
Calendar
|
||
|
||
Dashboard
|
||
|
||
Notification
|
||
|
||
must consume projections instead of storing duplicated business data.
|
||
|
||
---
|
||
|
||
## Backward Compatibility First
|
||
|
||
Existing APIs
|
||
|
||
Existing UI
|
||
|
||
Existing Schema
|
||
|
||
must remain compatible unless a controlled migration is explicitly approved.
|
||
|
||
---
|
||
|
||
# Review Required
|
||
|
||
Review
|
||
|
||
- Business Constitution
|
||
- BU-R.1 Capability Audit
|
||
- Current Schema
|
||
- Current CRM Modules
|
||
- Current Foundation Modules
|
||
- Existing API Contracts
|
||
- Existing Permission Model
|
||
- Existing Notification Foundation
|
||
- Existing Approval Runtime
|
||
- Existing Dashboard
|
||
- Existing PDF Engine
|
||
|
||
---
|
||
|
||
# Scope
|
||
|
||
## Part 1 — Current Architecture Map
|
||
|
||
Document the current architecture.
|
||
|
||
Identify
|
||
|
||
Relationship Layer
|
||
|
||
CRM Layer
|
||
|
||
Foundation Layer
|
||
|
||
Reporting Layer
|
||
|
||
Notification Layer
|
||
|
||
Approval Layer
|
||
|
||
Storage Layer
|
||
|
||
Security Layer
|
||
|
||
Document
|
||
|
||
Responsibilities
|
||
|
||
Ownership
|
||
|
||
Dependencies
|
||
|
||
Extension points
|
||
|
||
---
|
||
|
||
## Part 2 — Target Architecture
|
||
|
||
Produce the target architecture.
|
||
|
||
Include
|
||
|
||
Relationship Layer
|
||
|
||
Activity Layer
|
||
|
||
Project Layer
|
||
|
||
Commercial Layer
|
||
|
||
Workspace Layer
|
||
|
||
Analytics Layer
|
||
|
||
Foundation Layer
|
||
|
||
Security Layer
|
||
|
||
Document
|
||
|
||
Responsibilities
|
||
|
||
Boundaries
|
||
|
||
Ownership
|
||
|
||
Interaction
|
||
|
||
---
|
||
|
||
## Part 3 — Transition Architecture
|
||
|
||
Design the transition path.
|
||
|
||
For every capability determine
|
||
|
||
Preserve
|
||
|
||
Extend
|
||
|
||
Refactor
|
||
|
||
Replace
|
||
|
||
Migration Required
|
||
|
||
Backward Compatible
|
||
|
||
Breaking Change Risk
|
||
|
||
---
|
||
|
||
## Part 4 — Activity Platform Architecture
|
||
|
||
Define
|
||
|
||
Activity Domain
|
||
|
||
Activity Service
|
||
|
||
Activity Repository
|
||
|
||
Activity API
|
||
|
||
Activity Projection
|
||
|
||
Activity Ownership
|
||
|
||
Activity Lifecycle
|
||
|
||
Integration with
|
||
|
||
Customer
|
||
|
||
Lead
|
||
|
||
Opportunity
|
||
|
||
Quotation
|
||
|
||
Notification
|
||
|
||
Calendar
|
||
|
||
Timeline
|
||
|
||
Dashboard
|
||
|
||
---
|
||
|
||
## Part 5 — Timeline Projection Architecture
|
||
|
||
Define
|
||
|
||
Timeline Source
|
||
|
||
Timeline Generator
|
||
|
||
Timeline Projection
|
||
|
||
Timeline Query
|
||
|
||
Timeline Security
|
||
|
||
Timeline Caching
|
||
|
||
Timeline Event Mapping
|
||
|
||
Confirm
|
||
|
||
Timeline is generated.
|
||
|
||
Timeline is never manually edited.
|
||
|
||
---
|
||
|
||
## Part 6 — Calendar Projection Architecture
|
||
|
||
Define
|
||
|
||
Calendar Source
|
||
|
||
Activity Projection
|
||
|
||
Milestone Projection
|
||
|
||
Reminder Projection
|
||
|
||
Approval Projection
|
||
|
||
Forecast Projection
|
||
|
||
Calendar Aggregation
|
||
|
||
Calendar Filters
|
||
|
||
Calendar Permissions
|
||
|
||
Calendar Query Strategy
|
||
|
||
---
|
||
|
||
## Part 7 — Business Event Architecture
|
||
|
||
Freeze
|
||
|
||
Domain Event Ownership
|
||
|
||
Business Event Types
|
||
|
||
Publisher
|
||
|
||
Subscriber
|
||
|
||
Timeline Consumer
|
||
|
||
Dashboard Consumer
|
||
|
||
Notification Consumer
|
||
|
||
Automation Consumer
|
||
|
||
Determine
|
||
|
||
Event Contracts
|
||
|
||
Event Naming
|
||
|
||
Event Versioning
|
||
|
||
Event Payload Strategy
|
||
|
||
---
|
||
|
||
## Part 8 — Workspace Architecture
|
||
|
||
Design
|
||
|
||
Customer Workspace
|
||
|
||
Sales Workspace
|
||
|
||
Manager Workspace
|
||
|
||
Executive Workspace
|
||
|
||
Calendar Workspace
|
||
|
||
My Day
|
||
|
||
Navigation
|
||
|
||
Permission Boundary
|
||
|
||
Workspace Composition
|
||
|
||
---
|
||
|
||
## Part 9 — Integration Strategy
|
||
|
||
Determine
|
||
|
||
Existing Module Reuse
|
||
|
||
Adapter Layer
|
||
|
||
Projection Layer
|
||
|
||
Service Composition
|
||
|
||
Shared Components
|
||
|
||
API Compatibility
|
||
|
||
Feature Flags
|
||
|
||
Migration Strategy
|
||
|
||
---
|
||
|
||
## Part 10 — Implementation Strategy
|
||
|
||
Group implementation into Epics.
|
||
|
||
Example
|
||
|
||
Epic
|
||
|
||
Activity Platform
|
||
|
||
Epic
|
||
|
||
Timeline Projection
|
||
|
||
Epic
|
||
|
||
Calendar Workspace
|
||
|
||
Epic
|
||
|
||
Customer Workspace
|
||
|
||
Epic
|
||
|
||
Manager Workspace
|
||
|
||
Epic
|
||
|
||
My Day
|
||
|
||
Epic
|
||
|
||
Business Events
|
||
|
||
Epic
|
||
|
||
Notification Expansion
|
||
|
||
Epic
|
||
|
||
Forecast Enhancement
|
||
|
||
---
|
||
|
||
# Deliverables
|
||
|
||
Produce
|
||
|
||
## 1
|
||
|
||
Current Architecture Diagram
|
||
|
||
---
|
||
|
||
## 2
|
||
|
||
Target Architecture Diagram
|
||
|
||
---
|
||
|
||
## 3
|
||
|
||
Transition Architecture Diagram
|
||
|
||
---
|
||
|
||
## 4
|
||
|
||
Domain Ownership Matrix
|
||
|
||
---
|
||
|
||
## 5
|
||
|
||
Layer Responsibility Matrix
|
||
|
||
---
|
||
|
||
## 6
|
||
|
||
Business Event Architecture
|
||
|
||
---
|
||
|
||
## 7
|
||
|
||
Activity Architecture
|
||
|
||
---
|
||
|
||
## 8
|
||
|
||
Timeline Projection Architecture
|
||
|
||
---
|
||
|
||
## 9
|
||
|
||
Calendar Projection Architecture
|
||
|
||
---
|
||
|
||
## 10
|
||
|
||
Workspace Architecture
|
||
|
||
---
|
||
|
||
## 11
|
||
|
||
Dependency Graph
|
||
|
||
---
|
||
|
||
## 12
|
||
|
||
Migration Strategy
|
||
|
||
Categorize
|
||
|
||
Preserve
|
||
|
||
Extend
|
||
|
||
Refactor
|
||
|
||
Replace
|
||
|
||
---
|
||
|
||
## 13
|
||
|
||
Breaking Change Assessment
|
||
|
||
Risk
|
||
|
||
Mitigation
|
||
|
||
Compatibility
|
||
|
||
---
|
||
|
||
## 14
|
||
|
||
Epic Roadmap
|
||
|
||
Priority
|
||
|
||
Dependency
|
||
|
||
Estimated Order
|
||
|
||
---
|
||
|
||
## 15. Domain Dependency Matrix
|
||
|
||
Produce a dependency matrix describing how each business domain depends on and is consumed by other domains.
|
||
|
||
The objective is to visualize architectural coupling before implementation begins.
|
||
|
||
For every major domain identify:
|
||
|
||
- Domain Owner
|
||
- Depends On
|
||
- Used By
|
||
- Shared Services
|
||
- Projection Consumers
|
||
- Potential Breaking Change Impact
|
||
|
||
Minimum domains:
|
||
|
||
| Domain | Depends On | Used By |
|
||
|----------|------------|---------|
|
||
| Customer | Foundation | Contact, Activity, Lead, Opportunity |
|
||
| Contact | Customer | Activity, Lead |
|
||
| Activity | Customer, Contact, Lead, Opportunity, Quotation | Calendar, Timeline, My Day, Notification |
|
||
| Lead | Customer | Opportunity |
|
||
| Opportunity | Customer, Lead | Quotation, Dashboard, Forecast |
|
||
| Quotation | Opportunity | Approval, PDF, Timeline |
|
||
| Approval | Quotation | Notification |
|
||
| Timeline | Business Events | Customer Workspace |
|
||
| Calendar | Activity + Milestones | My Day, Manager Workspace |
|
||
| Dashboard | Opportunity + Activity + Events | Manager, Executive |
|
||
|
||
Deliverables
|
||
|
||
- Domain Dependency Diagram
|
||
- Domain Dependency Matrix
|
||
- Coupling Analysis
|
||
- High-Risk Dependency List
|
||
- Recommended Decoupling Strategy
|
||
|
||
---
|
||
|
||
## 16. Preserve / Extend / Refactor Matrix
|
||
|
||
Produce the official architectural transition strategy for every major module.
|
||
|
||
Every module must be classified into one of the following categories:
|
||
|
||
- Preserve
|
||
- Preserve + Extend
|
||
- Controlled Refactor
|
||
- New Capability
|
||
- Replace (only if explicitly justified)
|
||
|
||
The objective is to minimize disruption to the existing production architecture.
|
||
|
||
Minimum matrix:
|
||
|
||
| Module | Strategy | Notes |
|
||
|----------|----------|-------|
|
||
| Organization | Preserve | Core Foundation |
|
||
| RBAC | Preserve | Existing Permission Model |
|
||
| Customer | Preserve + Extend | Add Customer Workspace capabilities |
|
||
| Contact | Preserve | Existing Sharing Rules |
|
||
| Lead | Preserve + Minor Enhancement | Align Business Blueprint |
|
||
| Opportunity | Preserve + Extend | Forecast, Activity, Hot Project |
|
||
| Quotation | Preserve | Document Lifecycle Owner |
|
||
| Approval | Preserve | Existing Approval Engine |
|
||
| PDF | Preserve | Existing Document Engine |
|
||
| Dashboard | Preserve + Extend | Business-driven Metrics |
|
||
| Notification | Preserve + Extend | Consume Business Events |
|
||
| Activity | New Capability | Shared Operational Domain |
|
||
| Timeline | New Projection | Generated View |
|
||
| Calendar | New Projection | Workspace Layer |
|
||
| My Day | New Workspace | Personalized Operational Workspace |
|
||
| Manager Workspace | New Workspace | Operational Control Tower |
|
||
| Executive Workspace | New Workspace | Strategic Monitoring |
|
||
|
||
Deliverables
|
||
|
||
- Preserve Matrix
|
||
- Extension Matrix
|
||
- Refactor Matrix
|
||
- New Capability Matrix
|
||
- Breaking Change Impact Matrix
|
||
- Migration Recommendation
|
||
|
||
Frozen Rule
|
||
|
||
Every implementation epic after AR.1 must explicitly reference this matrix before modifying any production module.
|
||
|
||
If a proposed implementation changes a module classified as "Preserve", the implementation must include an Architecture Decision Record (ADR) explaining the reason, impact analysis, rollback strategy, and backward compatibility assessment.
|
||
|
||
# Constraints
|
||
|
||
This phase is architecture only.
|
||
|
||
DO NOT
|
||
|
||
- modify schema
|
||
- modify migrations
|
||
- modify APIs
|
||
- modify services
|
||
- modify UI
|
||
- modify permissions
|
||
- modify business logic
|
||
|
||
No production implementation is allowed.
|
||
|
||
---
|
||
|
||
# Success Criteria
|
||
|
||
A complete transition architecture exists.
|
||
|
||
Every new capability has a defined architectural location.
|
||
|
||
Every existing capability has a preservation strategy.
|
||
|
||
Every integration point is documented.
|
||
|
||
Every migration path is documented.
|
||
|
||
Breaking changes are minimized.
|
||
|
||
Core CRM foundation remains preserved.
|
||
|
||
Architecture is implementation-ready.
|
||
|
||
Ready for
|
||
|
||
AR.2 – Epic & Technical Design
|
||
|
||
|
||
## Architecture Governance Rule
|
||
|
||
AR.1 becomes the official architecture transition baseline.
|
||
|
||
Every future Epic, ADR, schema change, API change, or implementation task must reference:
|
||
|
||
- Business Constitution (BU-R.0 / BU-R.0.1)
|
||
- Business Capability Audit (BU-R.1)
|
||
- Architecture Transition Plan (AR.1)
|
||
|
||
Any implementation that violates the approved transition strategy must provide explicit architectural justification and receive governance approval before implementation begins.
|